La Granada Elementary

La Granada Elementary

Facility Needs Summary

1. Needs Identified in Prior Assessments
   1. Differed Maintenance Schedule – To be confirmed with M&O.
2. Site Development
   1. Parking, Drop-off, Service & Delivery
       1. Current parking and drop off needs redesign.
       2. Front vacant lot originally scheduled for County Office of Education facility is not currently being used.
   2. Site Security & Access Control
       1. Some security fencing is too low and allows vandal access.
       2. Security cameras would be beneficial to reduce vandalism
   3. Utility Services, Grading, Drainage, & Landscaping
       1. Flooding in play fields
       2. Existing Backflow leaks
       3. Area behind 2-story with trees could be better utilized for outdoor instruction and student activities with paving and improvements to LS & irrigation
   4. PE Fields, hardcourts and Grounds
       1. AC paving improvements and repairs needed.
3. Facilities
   1. Building Envelope
       1. Many buildings have roof leaks
   2. Building Systems & Equipment
       1. Doors and windows in older buildings need replacement
       2. Some newer doors in 2-story need repair.

Click arrow above to expand window ⤢
Sources: Demographic/enrollment data provided by Davis Demographics Student Population Forecasts document for Fall 2021/22 Enrollment. Publish date 2/25/2022.
Additional Sources: Student need and demographic data provided by the CA Department of Education.

Scope of Work

The scope of work identified for the renovation/expansion of each campus is categorized and budgeted based on the following descriptions:

Minor Modernization

General modernization of existing buildings and spaces is based on the ongoing use of spaces consistent with their current uses and includes the following areas of work:

  • Replace interior finishes including floors, walls and ceilings.
  • Repair, refinish or replace casework.
  • Up-grade building systems including power, lighting, HVAC, plumbing, fire protection, and educational technology.
  • Repair or replace communication and emergency notification systems including public address and fire alarm systems.
  • Up-grades to site security systems including intrusion alarms, surveillance cameras and security lighting.
  • Replace door hardware as needed.
  • Minor remodeling of spaces including signage for wayfinding and compliance with ADA.
  • Patch and repair exterior wall finishes and roofs.
Major Modernization

More extensive renovation of spaces to include all minor modernization work with additional renovation/reconfiguration or adaptive reuse of spaces to accommodate new/different uses. The additional level of work beyond minor modernization may include the following:

  • Demolition of interior spaces, systems, equipment.
  • Reconstruction of interior spaces to accommodate new program needs.
  • Replacement of doors and windows as necessary.
  • Up-grade of building structural systems impacted by the reconfiguration of spaces (excluding AB300 reconstruction or building-wide seismic up-grades).
  • Reconstruction or replacement of building systems.
New Construction

Scope addresses all construction that increases the building SF of the campus.  These include the following:

  • Construction of stand-alone buildings, shade structures or other major structures not otherwise listed in Site Improvements.
  • Expansion of existing buildings.
Site Improvements

Scope addresses renovation and expansion of playgrounds, fields, parking lots, and site entry enhancements including the following general areas of work:

  • Demolition of existing site improvements, surface and subsurface materials.
  • Repair/replacement of utility infrastructure.
  • Regrading and drainage improvements
  • Repair or replacement of landscaping and irrigation
  • Repair or replacement of paving, flatwork, and play surfacing.
  • Access and path of travel improvements for ADA compliance.
  • Exterior lighting where appropriate.
  • Playground apparatus and fixed physical education/sports equipment.
  • Security fencing and gates.
  • New or repair of electronic marquees as needed.
Soft Costs (Non-Construction)

These are project development costs that are beyond those associated with direct construction. These include the following:

  • Architectural/Engineering
  • Boundary/topographic site surveys and geotechnical investigations.
  • Hazardous materials assessment and mitigation.
  • Environmental reporting documents (CEQA compliance)
  • Agency review and approval fees such as DSA, CDE, City/County, Dept. of Health, DTSC, Public Utilities, etc.
  • Construction period testing and inspection services.
  • Legal and accounting services.
  • Program management, citizens oversight reporting, and other bond program services.
  • Movable furniture, fixtures and equipment (FF&E).
  • Insurance.
  • Phasing allowance for Interim housing.
  • Construction contingency for unforeseen field conditions.